October 11, Pavilion is Complete!

October 11, Pavilion is Complete!

October 11th: After three days of on-site construction, we are pleased to say that the NRC buoyant pavilion is ready to take on the winter and the coming freeze! The railings and the cross-bracing, shown below, were the final components to attach. We find the pavilion...
October 10, Day Two of Construction

October 10, Day Two of Construction

October 5: On day two of the NRC pavilion construction, we mounted and assembled the entire roof structure. It was a day of heavy lifting, and a bit of confusion about the assembly process, but the roof was fully constructed by an early end of the day for the holiday...
October 3, Day One of On-Site Construction

October 3, Day One of On-Site Construction

October 3: The first day of on-site construction and assembly of the NRC, pavilion took off under the supervision of architect Reuben Grin and with the help of various members of SGConstruction and University of Waterloo students Shabaan Khokhar (MA) and Tobias...